Capital

If you have trouble seeing the bids please email Webmaster: Richard Hernandez

SERVICE & DESCRIPTION BID DATE STATUS DETAILS
Development of 10 Acres Martin Midstream Property
Project # 12-028A
The scope of work consists of preparing subgrade, adding new geogrid and base material. In addition, work will also include upgrading of the existing fencing and lighting for staging of cargo under all weather conditions.
Project Mgr: Bert Perez, P.E.
July Day,2012 Pending ---
Replace Belts on CB 7, 8, 9 and Shiploader
Project # 12-016A
Consists of removing old conveyor bels and installing new conveyor belts.
Project Mgr: Dave Michaelsen, P.E.
June Day,2012 Pending ---
Replace PLC & Drives at Gantry Crane
Project # 12-022A
Once the new system is purchased and set up in a shop and the software program loaded into the processer a bench test would be conducted to confirm the system was properly configured. Then a two week window between ships would need to be scheduled to allow the old system to be removed and the new equipment installed and tested in the gantry crane.
Project Mgr: Dave Michaelsen, P.E.
June Day,2012 Pending ---
New Fire Barge Dock
Project # 12-027A
The scope of work consists of selecting a new location and constructing a new dock to berth the Fire Barge with good access to all associated fire service equipment needed to maintain it.
Project Mgr: Bert Perez, P.E.
May Day,2012 Pending ---
Viola Barge Dock Upgrades
Project # 11-054A
The scope of work includes the final engineering, surveying, testing, and construction to improve road access and increase the size of the facility to moor four (4) 30,000 barrel barges. Work anticipated to include approximately 500 linear feet of steel sheet pile bulkhead, slip dredging, several 4-pile barge breasting/mooring structures and a dock house.
Project Mgr: David L Krams, P.E.
May Day,2012 Pending ---
Provide Dock Space for Gangway at Oil Dock 1
Project # 11-013A
Consists of designing and constructing the hoist foundation and gangway support platform or ramp at Oil Dock 1
Project Mgr: Bert Perez, P.E.
April Day,2012 Pending ---
Replacement of Rail Dump Air Filtration System
Project # 12-032A
The scope of work will consist of installing two cyclones and the associated valve components and ducting required
Project Mgr: Bert Perez, P.E.
April Day,2012 Pending ---
Truck Loading Station at Bulk Dock 2
Project # 12-001A
The concept is to remove the existing portable conveyor from under Transfer Station #3 and replace it with a new fixed conveyor with the tail end of the conveyor positioned up one elevation. This will gain approximately 12’ in height. The discharge end of the conveyor would be above a dual 125 ton surge hopper. This will allow two trucks to be loaded at once or at least one truck can be loaded while another is being positioned.
Project Mgr: Dave Michaelsen, P.E.
April Day,2012 Pending ---
Pelican Island Erosion Protection - Phase II
Project # 11-051A
This will include extending the stone revetment/breakwater that was constructed in Phase I along a portion of the Pelican Island northern shoreline to protect critical habitat and wetlands from erosion. The work consists of construction surveying, dredging and filling an access and flotation channel, placing geotextile fabric and fill, construction of a stone breakwater/revetment, and cleanup.
Project Mgr: Paul Carangelo
April Day,2012 Pending ---
Replacement of Fendering on Bulk Dock 1
Project # 11-019A
The scope of work for replacing the fendering system at BD-1 will be similar to that performed at other docks. The timber fendering will be removed and the anchor bolts cut flush with the concrete face of the dock. New 20" to 24" rubber arch or trapezoidal fender elements will be installed, most in two horizontal rows—one at the waterline and another near deck level. In addition, a vertical element will be placed at every bent line along the 396'-long dock.
Project Mgr: Jacob Morales, P.E.
February 03,2012 Active Details
Addendum No 1
Hoist Foundations & Gangway Support at Oil Docks 4, 7 & 11
Project # 08-001A
Consiste of constructing a new hoist foundation, gangway support platform, dock expansion platform and a personnel walkway at Oil Dock 11. These dock components will be steel fabricated structures supported by driven steel pipe piles.
Project Mgr: Jacob Morales, P.E.
February 03,2012 Active Details
Addendum No 1
Addendum No 2
Purchase of Vehicles
Project # 12-009A
Purchase of seven (7) vehicles which include a one-ton crew cab flatbed truck, one-ton four wheel drive crew cab truck, one-ton cab & chassis dual rear wheel crew cab truck, two half-ton crew cab trucks, four wheel drive half-ton crew cab truck, and a high occupancy SUV.
Project Mgr: Jacob Morales, P.E.
February 03,2012 Active Details
Addendum No 1
Addendum No 2
Removal of Pipelines Along Navigation Boulevard
Project # 09-026B
The work consists of removal and proper disposal of the contents within several abandoned pipelines and also to remove and properly dispose of the buried pipelines.
Project Mgr: David L, MIchaelsen, P.E.
December 02,2011 Active Details
Addendum No 1
Fire System Pressurization on Avery Point Oil Docks
Project # 08-046A
Includes the design and preparation of contract documents for the above ground storage tank. Project elements anticipated include the installation of new pump, associated piping and reservoir tank.
Project Mgr: Bert Perez, P.E.
November 15,2011 Awarded Details
Addendum No 1
Addendum No 2
Replacement of Bulkhead at Viola Turning Basin
Project # 08-011A
Scope of work consists of procuring and installing the specified 474 LF steel sheet piling to stabilize banks along the Viola Turning Basin. Sheet pile wall will be cantilever type.
Project Mgr: Jacob Morales, P.E.
September 02,2011 Awarded Details
Addendum No 1
Tule Lake Channel Improvements
Project # 07-046C
Work includes the demolition of the marine foundations and fendering with the complete removal of all concrete and steel structures on both sides of the Ship Channel down to an elevation of -52 to -54 Navo 86
Project Mgr: Dave Michaelsen, P.E.
July Day,2011 Hold ---
New Oil Dock 9 Dock House
Project # 11-032A
The scope of work entails the construction of a new dock house consisting of concrete tilt-up walls, restroom amenities, electrical service, communication service, lighting, heating and air conditioning. Also included will be new doors and windows.
Project Mgr: Jacob Morales, P.E.
June 03,2011 Awarded Details
Addendum No 1
Replace Cable Drums & Lengthen the Gantry Crane Boom at Bulk Dock 1
Project # 09-033A
The Base Bid work consists of removing and replacing the hold and close cables drums. Additive Bid Item 1 is to strengthen the structural components on the Gantry Crane in several locations, add a 10'-5" boom extension, and other improvements as shown on the drawings and contract documents.
Project Mgr: Dave Michaelsen, P.E.
June 02,2011 Awarded Details
Purchase of Vehicle
Project # 11-008A
This is a lump sum purchase for one (1) four wheel drive police special service vehicle.
Project Mgr: Jacob Morales, P.E.
February 25,2011 Awarded Details
Cold Storage Facility Repairs
Project # 11-001A
The Base Bid work primarily consists of rebuilding an Evaporative Condenser unit and replacing valves for several of the roof top freezer coils. Additive Bid items consist of door and door panel replacement repairs, truck dock door repairs, insulation repairs, roof repairs, concrete repairs, replacement of corroded pipe, and painting.
Project Mgr: Dave Michaelsen, P.E.
January 31,2011 Awarded Details
Addendum No. 1
Repower of Bulk Terminal Locomotive Switch Engine
Project # 10-040A
The basic scope of work is repowering an existing 1,000 horsepower locomotive switch engine with two new 700 horsepower nominal industrial Generator Set diesel engines totaling 1,400 horsepower nominal that meet certified Tier II off-road technology. A Tier IV diesel particulate filter will also be added.
Project Mgr: Dave Michaelsen, P.E.
January 28,2011 Awarded Details
Addendum No 2
Purchase of Bulk Fuel
Project # 10-038A
Purchase consists of bulk quantities of Ultra Low Sulfur Diesel and Unleaded Gasoline for one year.
Project Mgr: Jacob Morales, P,E.
December 06,2010 Awarded Details
Addendum No 1
Joe Fulton International Trade Corridor - Phase II
Project # 09-026A
The Scope of Work consists of overlaying approximately 6.5 miles of existing roadway with 5.5" of hot mix asphalt, the reconstruction of approximately 2.25 miles of substandard roadway along Navigation Blvd., the removal of several pipelines and the installation of a new 16" dia. waterline.
Project Mgr: Dave Michaelsen, P.E.
October 30,2009 Awarded Details