Capital

If you have trouble seeing the bids please email Webmaster: Richard Hernandez

SERVICE & DESCRIPTION BID DATE STATUS DETAILS
Harbor Island - Demolition of Existing Docks
Project # 18-033B
The scope of work generally consists of removal and disposal of landside, waterside, and submerged items on the PCCA Harbor Island property, generally consisting of three (3) deep waterfront pier and dock structures no longer in use and consisting of steel and reinforced concrete. Work also includes landside demolition and removal of a 7,200-square foot metal building (foundation to remain) and other miscellaneous items.
Project Mgr: Eileen Mink, EIT
November 28,2018 Active Details
Pre-Bid Sign In Sheet
La Quinta Ship Dock Berth Dredging Project
Project # 18-028A
This project consists of performing improvements to Dredge Material Placement Area 14 perimeter levees and outfall structures and the dredging and placement of approximately 484,503 CY of material to create a deep draft slip berth at a dock facility under construction at the PCCA’s La Quinta Terminal. The berth will be dredged to an elevation of -45 feet mean lower low water plus 4 feet advanced maintenance dredging for a required elevation of -49 feet mean lower low water.
Project Mgr: Javier Davila, P.E.
September 10,2018 Awarded Details
Pre-Bid Sign In Sheet
Addendum No 1
Addendum No 2
Hurricane Harvey Repairs to Armoring of the Nueces Bay Shoreline/Bike Path
Project # 16-1699S
Scope of work generally includes cut and fill to reshape approximately 200-linear feet of an existing shoreline providing additional fill to stabilize embankment, furnishing and placement of geotextile fabric, size 2-inch to 6-inch bedding stone, size 6-inch to 18-inch armor riprap, and repairs to asphalt bike path as necessary. This is a lump sum contract.
Project Mgr: Eileen Mink, EIT
July 31,2018 Awarded Details
Pre-Bid Sign In Sheet
Contract-Aransas-Corpus Christi Pilots Pier at Harbor Island
Project # 18-029A
This scope of work includes the construction of a timber walking pier with parking area, area lighting, perimeter fencing with automatic gate, site drainage, and seeding
Project Mgr: Carlos Martinez, P.E.
July 03,2018 Rejected/Cancelled Details
Pre-Bid Sign In Sheet
Addendum No 1
RFQ - Geotechnical Investigation Services for Ship Channels Dredge Material Placement Areas
Project # 18-001B
The Port of Corpus Christi Authority (“Port Authority”) is requesting Statements of Qualifications from consultant firms interested in providing Geotechnical Investigation Services evaluate subsurface conditions in Ship Channels and Dredge Material Placement Areas, and material characteristics of potential dredge material related to the Ship Channel Deepening and Widening Project.
Project Mgr: Dan Koesema
April 02,2018 Active Details
Addendum No. 1
Security Grant 15 - Bulk Terminal Fencing - Additional Fencing
Project # 15-061E
The base bid scope of work consists of installing 1,280 linear feet of 8 foot tall security fencing with concrete curb and manual swing gates along Kirksey Road at the Bulk Terminal.
Project Mgr: Carlos Martinez, P.E.
March 06,2018 Awarded Details
Pre-Bid Sign In Sheet
Purchase of Bulk Fuel
Project # 18-502A
This purchase consists of bulk quantities of Ultra Low Sulfur Diesel and Unleaded Gasoline.
Project Mgr: Lynn Angerstein
February 22,2018 Awarded Details
New Access Road to Good Hope Dredge Material Placement Area
Project # 09-019A
New Access Road to Good Hope Dredge Material Placement Area includes construction of 2,500 linear feet of all-weather road, and associated site and drainage improvements.
Project Mgr: Javier Davila
February 07,2018 Awarded Details
Pre-Bid Sign In Sheet
Addendum No. 1
RFQ - New North Bank Cargo Dock
Project # 17-019A
The Port of Corpus Christi Authority (“Port Authority”) is requesting Statements of Qualifications (SOQ) from firms interested in providing Design-Build services for the Port Authority’s New North Bank Cargo Dock project.
Project Mgr: Natasha Fudge
February 05,2018 Awarded Details
Project Information Meeting Sign In Sheet
Addendum No. 1
Addendum No. 2
13-041C Rincon B Mitigation Construction
Project # 13-041C
The project scope includes all work associated with constructing aquatic habitat benches and water circulation channels, planting of salt-marsh vegetation, and placement of excess excavated material within the limits of an existing adjacent dredge material placement area. The project is located just north of PCCA’s Rincon B West Dredge Material Placement Area adjacent to the PCCA Rincon Industrial Park Canal B in Nueces County.
Project Mgr: Paul Carangelo
December 22,2017 Awarded Details
Pre-Bid Sign In Sheet
Rincon West Storage Area Development
Project # 17-028C
The project scope includes the phased development of a 25-acre storage yard, to include earthwork, grading, limestone paving improvements. The project is located on the PCCA’s Rincon Channel property in Nueces County. Bidders must submit a bid for the Base Bid and Additive Bid.
Project Mgr: Danielle Caro
December 04,2017 Active Details
Pre-Bid Sign In Sheet
Addendum No. 1
Addendum No. 2
RFQ-New Port Office Facility
Project # 14-036A
The Port of Corpus Christi Authority (“Port Authority”) is requesting Statements of Qualifications (SOQ) from firms interested in providing Design Build services for the Port Authority’s New Office Facility project.
Project Mgr: Brett Flint
December 01,2017 Active Details
Project Inf. Mtg. Sign In Sheet
Addendum No. 1
Addendum No. 2
La Quinta Terminal Upland Buffer Area (Re-Bid)
Project # 14-047A (Re-Bid)
The project scope includes earthwork, irrigation, hay-mulch erosion control improvements, and grass and tree planting to create a levee-based buffer area from within the limits of an existing approximate 140 acre temporary dredge material placement area and reconfigure remaining acres into dredge material placement cells. The project is located on the PCCA’s La Quinta Terminal property in San Patricio County. Bidders must submit a bid for both the Base Bid and the Alternate Base Bid.
Project Mgr: Paul Carangelo
October 31,2017 Rejected/Cancelled Details
Pre-Bid Sign In Sheet
Fire Pressurization Upgrades at Oil Docks 1, 2 & 15
Project # 14-023A
The scope of work for this project is to construct a fire water storage and supply system for PCCA Oil Docks 1, 2 & 15. Work will generally include construction of a structural steel, auger-cast pile supported water storage tank, supplying and installing a housed pump system, underground piping to Oil Dock 1, 2 & 15 existing dry fire water piping system, horizontal bore under Navigation Boulevard and the existing railroad lines for connection to the City water supply, installation of a back flow preventer, upgrading existing fire nozzles and installing foam canister at Oil Docks 1, 2 & 15. In addition, electrical service will require construction of a new AEP approved transformer concrete foundation, and all associated electrical services to the fire pump system.
Project Mgr: Bert Perez, P.E.
October 11,2017 Awarded Details
Pre-Bid Sign In Sheet
Addendum No 1
Addendum No 2
Addendum No 3
La Quinta Terminal Upland Buffer Area
Project # 14-047A
The project scope includes earthwork, irrigation, hay-mulch erosion control improvements, and grass and tree planting to create a levee-based buffer area from within the limits of an existing approximate 140 acre temporary dredge material placement area and reconfigure remaining acres into dredge material placement cells. The project is located on the PCCA’s La Quinta Terminal property in San Patricio County. Bidders must submit a bid for both the Base Bid and the Alternate Base Bid.
Project Mgr: Paul Carangelo
October 05,2017 Rejected/Cancelled Details
Addendum No 1
Pre-Bid Sign In Sheet
Addendum No 2
Addendum No 3
Bulk Liquid Handling Facility at Bulk Dock 3
Project # 17-033B
Scope of work generally includes the construction and commissioning of a bulk liquids handling facility transfer of petroleum products from vessels to railcars. Site work improvements include fabrication of piping, racks, pile foundations, cast in place concrete, electrical improvements, area lighting, and mooring bollards. Equipment installation includes mechanical systems, instrumentation, control building, and vapor combustion unit. Work also includes the relocation of 105’ long pipe bridge.
Project Mgr: Carlos Martinez
September 18,2017 Awarded Details
Pre-Bid Sign In Sheet
Addendum No 1
Addendum No. 2
Addendum 3, 4, 5 & 6
Mike Carrell Road Entrance & Roadway
Project # 15-050A
This project consists of construction of a terminal entrance and roadway for access to Port of Corpus Christi Authority Public Oil Dock 14 and M&G Resins USA, LLC plastic resins facility. The work includes installation of channelization/left turn, deceleration and acceleration lane construction, temporary traffic control and construction sequencing on the Fulton Corridor, storm water pollution prevention, drainage, culvert installation and extensions, embankment, grading, paving, pavement markings, signage and striping, a dual-road track crossing with signals and gates, waterline, electrical service installation and lighting for the Fulton Corridor intersection improvements and Mike Carrell Road construction, including topsoil, seeding, and sod installation of disturbed areas. Work is to be phased to limit unstable disturbance to less than 10 acres.
Project Mgr: Dave Michaelsen, P.E.
September 12,2017 Awarded Details
Pre-Bid Sign In Sheet
Addendum No 1
Addendum No. 2
Addendum No 3
Storm Water System Quality Improvements
Project # 15-046A
The Storm Water System Quality Improvements project can be broken down into two tasks. Task one is to restore the capacity of the public storm water detention ponds. Task two is to provide storm water infrastructure improvements for the existing storm water filtration system at the bulk terminal. Proposed modifications will require removing and replacing concrete channels, removing driveway bridge structure and replacing with RCP driveway culvert, weirs, headwalls, misc. demolition, adding retaining walls, slabs, weirs, ramps, storm pipes, inlets, headwalls, pavement, curbs, asphalt humps, guard rails, site grading, temporary and permanent relocation of various utilities, and adjustment of existing utilities.
Project Mgr: Beatriz Rivera
June 12,2017 Awarded Details
Pre-Bid Sign-in sheet
Addendum No. 1
Addendum No. 2
Addendum No. 3
Bulk Terminal Paving Improvements
Project # 16-067A
The scope of work includes HMAC paving improvements at the Bulk Terminal.
Project Mgr: Carlos Martinez
June 05,2017 Awarded Details
Pre-Bid Sign In Sheet
General Improvements to Cargo Dock Transer
Project # 16-032A
Project Mgr: Bert Perez, P.E.
May Day,2017 Pending ---
Viola Barge Basin Bulkhead Addition
Project # 16-035A
Design and construct a steel sheet pile at the approximately 220-foot long shoreline bulkhead at the Viola Barge Basin.
Project Mgr: Danielle Caro
May 08,2017 Awarded Details
Addendum No 1
Pre-Bid Sign In Sheet
Addendum No. 2
Interim Improvements and Stabilization of Permian Yard
Project # 17-708A
The project site is on the north side of the Corpus Christi Ship Channel at the Permian Yard. Work generally includes cutting, filling, and grading the site to line grades shown on'the construction drawings, the removal of three concrete drainage structures, applying hydromulch vegetative cover, and watering vegetation to achieve permanent stabilization of the site.
Project Mgr: Steven Ashley
March 31,2017 Awarded Details
Addendum No. 1
Purchase of Floating Dock - Oil Transfer Operating Platform
Project # 17-033A
This is a purchase of 12,000 bbl double-hulled tank barges with hose tower, equipped with a 20,000lb load capacity hydraulic marine crane (Nautilus model 60B2-70 or equivalent), fitted with remote-operated Vessel Overfill Control System and include a vapor combustion dock safety unit skid
Project Mgr: Brett Flint, P.E.
March 16,2017 Awarded Details
Addendum No 1
Addendum No. 2
Addendum No. 3