Capital

If you have trouble seeing the bids please email Webmaster: Richard Hernandez

SERVICE & DESCRIPTION BID DATE STATUS DETAILS
Security Grant 7 Northside Security & Critical Docks Access Control
Project # 07-034C
Base Bid scope of work consists of installing a security gate, with asphalt parking, concrete paving, lighting, cameras, access control, fencing, gates, active net barrier system, concrete barriers, modular metal building and covered inspection area. Additive Bid Items include driver license scanners, K-4 crash rated gates, concrete barriers and active net barrier system.
Project Mgr: Pat Veteto, P.E.
Day,Year Pending Details
Fire Pressurization System at Oil Docks
Project # 08-046A
The scope of work consists of installing new pumps, piping, and tanks.
Project Mgr: Bert Perez, EIT
October ,2010 Pending ---
Boom Length Addition to Gantry Crane
Project # 09-033A
The scope of work consists of gantry crane structural reinforcement, trolley cable lengthening, boom length extension, and gantry crane stabilization.
Project Mgr: Dave Michaelsen, P.E.
August Day,2010 Pending ---
Fencing at Storage Yards and Other Port Areas
Project # 10-003A
The scope of work for this project includes the installation of new or replacement fencing at various locations throughout the Port that do not qualify for federal funding. The security fence standard consists of an 8’ tall fence with outriggers and barbed wire, on top of a reinforced concrete beam underneath the fence line.
Project Mgr: Jacob Morales
August Day,2010 Pending ---
Increase Digging Depth of Gantry Crane
Project # 06-021D
The scope of work consists of removing the hold and close lines (steel wire ropes) from the drums and installing lagging over the top of the grooved cylinders that hold the wire ropes.
Project Mgr: Dave Michaelsen, P.E.
August ,2010 Pending ---
AEP Property Development
Project # 08-041A
The scope of work consists of procurement of the property, site preparation, and installation of paving, fencing, and lighting.
Project Mgr: Jacob Morales
July Day,2010 Pending ---
Hoist Foundations & Gangway Support at Oil Docks 4, 7 & 11
Project # 08-001A
The scope of work consists of finalizing the design and constructing the hoist foundations and gangway support platform or ramp at Oil Dock 11.
Project Mgr: David Krams, P.E.
July Day,2010 Pending ---
Paving of Additional Storage Area Behind the Brown Express Building
Project # 09-018B
This project includes excavation, adding geogrid, additional limestone base material and asphalt surfacing to match the adjacent properties.
Project Mgr: Bert Perez, EIT
July 30,2010 Pending ---
Tule Lake Channel Improvement
Project # 07-046C
The second contract includes the demolition of the marine foundations and the complete removal of all concrete and steel structures on both sides of the Ship Channel down to an elevation of -72 feet MLT.
Project Mgr: Dave Michaelsen, P.E.
June Day,2010 Pending ---
Purchase and Installation of Vehicle Propane Conversion Kits
Project # 10-008B
Procurement and installation of EPA/CARB approved propane-powered conversion kits and propane fuel tanks for five (5) PCCA vehicles. Work will also require the pickup and delivery of the vheicles from PCCA Facility.
Project Mgr: Jacob Morales
June 30,2010 Hold Details
Addendum No. 1
Addendum No. 2
Purchase of Emergency Generator and Automatic Transfer Switch for Annex Building
Project # 09-023B
Purchase and delivery of a Natural Gas Generator and Automatice Transfer Switch for the Annex Building
Project Mgr: Bert Perez, EIT
June 23,2010 Awarded Details
Addendum No 1
Purchase of Equipment
Project # 10-008A
The scope of work includes the purchase of two new welding machines for Bulk Terminal.
Project Mgr: Jacob Morales
May Day,2010 Pending ---
Replace Air Conditioning Systems at Oil Docks 1, 2 & 3
Project # 10-027A
The scope of work consists of installing Class I, Division 1 air conditioning units, replacing broken windows, and sealing penetrations at the dock houses on Oil Docks 1, 2, and 3.
Project Mgr: Jacob Morales
May Day,2010 Pending ---
Reconstruction of Navigation Blvd. Between CD-9 & Fulton Corridor
Project # 09-028A
The scope of work includes the reconstruction of Navigation Blvd. from the Joe Fulton Corridor to Avenue F. The project includes the excavation and removal of existing 20-foot roadway, intersections, driveways, and dirt shoulders followed by the compaction of the existing subgrade and the addition of geogrid, limestone base and a hot mix asphalt surface. The new roadway will provide 2-12 foot lanes with 2-foot shoulders on each side.
Project Mgr: Bert Perez, EIT
April Day,2010 Pending ---
La Quinta Multipurpose Dock Facility Test Pile Program
Project # 07-036B
The scope of work generally consists of providing access to and constructing a test pile pad to perform a test pile program on two driven steel pipe piles and an augered cast-in-place concrete pile requiring four augered cast-in-place concrete reaction piles.
Project Mgr: David L. Krams, P.E.
April 06,2010 Awarded Details
Addendum No 1
Addendum No 2
Addendum No 3
Purchase of Vehicles
Project # 10-009A
The scope of work consists of the replacement/purchase of the below vehicles. One 1-ton pickup and one small bucket truck (software support team for port security) for the Maintenance Department, and one 4-wheel drive patrol SUV vehicle for the Police Department.
Project Mgr: Jacob Morales
March Day,2010 Hold ---
Security Grant - Phase 6 Cameras at the Bulk Terminal
Project # 06-052K
Work consists of installing 10 cameras, 5 camera poles, camera mounts, fiber-optic cable, power, and communications to and from the Security Command Center. This contract will require the testing of all communications to and from the cameras at the command center. Additive Bid Item includes adjusting the final camera alignment for correct field of view, tilt and azimuth.
Project Mgr: Pat Veteto, P.E. (RVE, Inc.)
January 26,2010 Awarded Details
Purchase of Power 6 Mes Upgrade Computers
Project # 001
The purchase of IBM Power 6 Mes Upgrade Computers.
Project Mgr: Marvin Mooney
January 12,2010 Active Details
Purchase of Cameras and Cables
Project # 06-052J
This is a lump sum purchase for surveillance thermal cameras and cables.
Project Mgr: Dave Michaelsen, P.E.
December 29,2009 Awarded Details
Joe Fulton International Trade Corridor - Phase II
Project # 09-026A
The Scope of Work consists of overlaying approximately 6.5 miles of existing roadway with 5.5" of hot mix asphalt, the reconstruction of approximately 2.25 miles of substandard roadway along Navigation Blvd., the removal of several pipelines and the installation of a new 16" dia. waterline.
Project Mgr: Dave Michaelsen, P.E.
October 30,2009 Awarded Details
Modifications of Cofferdam Fender Systems at Oil Docks 4 & 7
Project # 08-038A
The scope of work consists of removing a section of each cofferdam, constructing a concrete mounting panel, and installing the appropriately sized fender element and panel.
Project Mgr: Jacob Morales
October 30,2009 Awarded Details
Emergency Generator for Admin Bldg
Project # 09-023A
The Scope of Work for this project in to install a 1000 amp, 208 volt, 3 phase automatic transfer switch and provide all labor and materials to connect the ATS to the main service and to install a PCCA provided 275 kW natural gas emergency generator. Recommended Manufacturer maintenance and voltage reconfiguration will also be required. This is a Lump Sum bid item.
Project Mgr: Bert Perez, EIT
September 30,2009 Awarded Details
Suntide Bypass Road
Project # 08-035B
The scope of work consists of securing permits, clearing the land, placing and compacting fill material and base, and constructing a road surface with two 12' travel lanes and shoulders.
Project Mgr: Dave Michaelsen, P.E.
September 0,2009 Pending ---
Raising Height of Conveyor CB-1
Project # 09-011A
Scope of Work: In order to alleviate the flooding problems at the CB-1
Project Mgr: Dave Michaelsen, P.E.
August 04,2009 Awarded Details
Renovation of Dock Houses at Oil Docks 4, 7 & 11
Project # 08-028B
Scope of work of this project generally includes the selective demolition and reconstruction of dock house perimeter walls, fabrication and installation of cat walks, and procurement and installation of air conditioning units at Oil Docks 4, 7 & 11.
Project Mgr: Greg Brubeck, P.E.
June 30,2009 Awarded Details
Upgrade of Mooring Bitts on Various Docks
Project # 07-003A
The scope of work consists of replacement of mooring bitts at various docks.
Project Mgr: David L. Krams, P.E.
March 02,2009 Awarded Details